Electricity meter check from the Platform

This step follows the physical installation of the electricity meters and their configuration in the Climkit platform.

Final verification of electricity meters

On the platform, open the site and go to Tools > Meter Control > Electricity.

Consumption meter types

check_meters.png
  • All meters must show “True”.
  • All phases must have a voltage between 230V and 240V “L1V, L2V, L3V”.
  • Consumption meter types must have positive power on each phase “L1W, L2W, L3W”.
  • For consumption meter types (11, 12, 13, …), there must be no exported energy under “Exp”.
  • Check the password for each meter to see if it matches the configuration.
  • Without an energy production installation, the instantaneous powers on meter 10 must be positive.
  • If there is production and energy is fed back into the grid, the powers are negative.

Production meter type

check_meters_2.png

The production meter must have negative powers “L1W, L2W, L3W”.

Input meter type

The input meter must have negative powers “L1W, L2W, L3W” if energy is being fed back into the grid, or positive powers if energy is being drawn from the grid.