Verification of electricity meters from the platform

This step occurs after the physical installation of the electricity meters and their configuration in the Climkit platform.

Final verification of electricity meters

On the platform, open the site and go to Tools > Meter control > Electricity.

Consumption meters

check_meters.png
  • All meters must be "True".
  • All phases must have a voltage between 230V and 240V "L1V, L2V, L3V".
  • Consumption meters must have positive power on each phase "L1W, L2W, L3W".
  • For consumption meters (11, 12, 13, …), there should be no exported energy under "Exp".
  • Check the password for each meter to see if it matches the configuration.
  • Without an energy production installation, the instantaneous power on input meter 10 must be positive.
  • In the presence of production and in the event of energy fed back (electricity) to the grid, the power values are negative.

Production meter

check_meters_2.png

The production meter must have negative power values "L1W, L2W, L3W".

Input meter

The input meter must have negative power values "L1W, L2W, L3W" if energy is being fed back (electricity) to the grid or positive power values if drawing from the grid.