Installer start-up guide (read first)

Jean-Nicolas Turlier Updated by Jean-Nicolas Turlier

This guide is intended for installers who integrate Climkit solutions into their projects, from the preparation phase to commissioning.

It serves as support for both simple and complex installations, helping to identify key points, structure planning, and secure each step.

The content covers the principles of the different Climkit solutions, the information to be collected on site, configuration procedures on the platform, installation of equipment on site, as well as the checks to be carried out during commissioning.

This approach ensures an installation that complies with standards, reliable communication of equipment, and a controlled commissioning.

Equipment Planning and Installation

The installer is responsible for site planning and equipment installation on behalf of their client, the owner. Once the work is completed, the owner mandates Climkit as the manager of the energy installation.

Climkit supports the installer throughout the project to define solutions adapted to the site and the owner's needs, to validate certain technical choices when necessary, and to ensure the proper setup of the equipment.

This approach establishes a clear framework from the start while maintaining the necessary flexibility to adapt to the specific constraints of each installation.

Complete Installer Guide

This article introduces the documentation for Climkit installers, organized by project stage.

It is not necessary to read articles concerning solutions not planned for the site. However, for each selected solution, the entire corresponding path must be followed, from planning to on-site installation.

In case of questions during planning or installation, the Climkit teams can provide technical support and validate certain points before commissioning.

1. Project Preparation
2. Configuration on the Platform
3. On-site Equipment Installation
4. Verification and Testing

The fictitious project Le Chemin des Sourires illustrates the implementation of a Climkit system in a residential building.

Technical setup validation of the installation

After on-site installation and Technical setup validation of the equipment, Climkit performs a remote technical validation before the start of the Administrative setup.

The installer informs Climkit by email at service@climkit.io when the installation is complete and the configured equipment is correctly connected and transmitting its data.

A Climkit Support agent then checks the site configuration and the proper operation of the equipment remotely.

If corrections are necessary, Climkit contacts the installer and indicates the adjustments to be made before validation.

Once the technical validation is completed:

  1. The label provided with the order, bearing the mention "Warning - metering system in service", must be visibly stuck on the electrical panel.
  2. The site can move on to the Administrative setup stage.

Administrative setup and Operational phase

After the installation and technical validation of the equipment, the installer transmits the owner's details to Climkit. Climkit then supports the owner or their management agency in the Administrative setup of the site: entering consumer details, defining Billing rates, and management procedures.

Once these elements are defined, a Management contract is established. Climkit offers a full service for Consumer billing on behalf of the owner, guaranteeing precise individualization of consumption (electricity, heating, laundry, charging stations, etc.).

This centralized management ensures simplified and transparent operation for all stakeholders.