Checking electricity meters from the platform

This step follows the physical installation of the electricity meters and their configuration in the Climkit platform.

Final verification of electricity meters

On the platform, open the dashboard and go to Tools > Meter Control > Electricity.

Consumption-type meters

check_meters.png
  • All meters must show "True".
  • All phases must show a voltage between 230V and 240V "L1V, L2V, L3V".
  • Consumption-type meters must have positive power on each phase "L1W, L2W, L3W".
  • For consumption-type meters (11, 12, 13, …), there should be no exported energy under "Exp".
  • Verify the password for each meter to see if it matches the configuration.
  • Without an energy production installation, the instantaneous powers on meter 10 must be positive.
  • When production is present and in case of fed back energy to the grid, the powers are negative.

Production-type meter

check_meters_2.png

The production meter must show negative powers "L1W, L2W, L3W".

Input-type meter

The input meter must show negative powers "L1W, L2W, L3W" if energy is being fed back to the grid, or positive powers if energy is being drawn from the grid.