Install the three-phase Relay meter

This article describes the on-site installation of a three-phase relay meter. For the equipment to function, a configuration on the Climkit platform is also necessary. Links are available at the end of the document.

Installation of a three-phase relay meter

  1. Connect the meter according to the diagram below.
  2. Connect the meter to the RS485 bus of the Climkit gateway. Unlike other meters, it is necessary to connect only A and B.

How Did We Do?

Install the RFID reader

Installing the Shelly relay meter