Install a three-phase relay meter

This article describes the on-site installation of a three-phase relay meter. Configuration on the Climkit platform is also required for the equipment to function. Links are available at the end of the document.

Installation of a three-phase relay meter

  1. Wire the meter according to the diagram below.
  2. Connect the meter to the Climkit gateway's RS485 bus. Unlike other meters, it is only necessary to connect A and B.

How Did We Do?

Install an RFID badge reader

Install a Shelly relay meter

Contact