Installation of Shelly relay meters

Christopher Gautschi Updated by Christopher Gautschi

Each Shelly relay meter comes with two labels located on the back of the device.

Steps to follow for each socket equipped with a Shelly:

  1. Peel off one of the two labels located on the back of the Shelly.

    Leave the other label on the Shelly; it is necessary for on-site identification.

  2. Stick the peeled-off label onto an A4 sheet, clearly specifying:
    • The socket number where the Shelly is installed.
  3. Take a clear photo of the entire sheet.
  4. Send the photo to Climkit via email to enable remote platform configuration.

Example of a completed sheet:

Socket

Label

Socket 1

[Label 1]

Socket 2

[Label 2]

Important:

  • A mismatch between labels and sockets will lead to errors in platform configuration.
  • Each Shelly must be clearly identified, and the information must be legible on the sent photo.