Configuration of Electric Meters

1. Configuration on the portal

Log in to the Climkit online portal (app.climkit.io), select the corresponding site. Under Meters, create the meters one by one by clicking on the "+".

  • Name: name according to labeling and their allocation. For example: "3P7 - Apartment 203"
  • Address: Set the Modbus address for each meter if possible according to the following model:
    • General introduction meter: 10
    • Production meter(s): 101, 102, ...
    • Consumption meter(s): 11, 12, ...
    • Battery meter(s): 120, 121, ...
  • Gateway: Select the gateway to which the meters are connected. See under Configuration > Hardware.
  • Model: eastron_modbus (default)
  • Protocol: modbus (default)
  • Baudrate: 9600 (default)
  • Mode: according to the type of meter (introduction, consumption, production or battery)
  • Max Current (A): the amperage of the connection (e.g. 25 A).

2. Modbus addressing of the meters

The addressing of the meter is done directly on the meter.

password.png

Under “SET Addr”, enter the meter address set on the online portal (see above).

To modify the address, press the “E” key for 3 seconds, then select the unit to modify using the “E” key, then modify the unit using the “P” or “M” keys.

Once the address is correctly edited, confirm by pressing the “E” key for 3 seconds.

set_addr.png

Change the password for each meter under “SET PASS” with the password indicated under “Configuration” > Gateway:

set_pass_1000.png

TI Ratio (indirect meter only)

Change the TI ratio under “CT rate” according to the type of meter:

  • Eastron SDM630MCT V2 (with TI /5A)
ct_rate.png

Note, the ratio can only be saved once on these MID certified meters! CT rate = primary current of the TI divided by its secondary current (5A) (e.g.: Primary current of the TI 200A, CT rate = 200/5 = 40)