Install heat and water meters

This article describes the on-site installation of heat and water meters. For the equipment to function, a configuration on the Climkit platform is also required, which is usually performed by our teams.

Connection of water and heating meters

  1. Install the heat and water meters according to the manufacturer's and supplier's instructions.
  2. Connect the M-Bus port of each meter to the RS485-MBus converter according to the instructions in Install the M-Bus converter.
  3. Organize commissioning with the meter supplier to verify that each meter is correctly installed and is measuring the consumed energy or volume.
  4. Submit the commissioning protocols to Climkit so that each meter can be added to the platform and read by the Climkit gateway.